Setup IPR Database
 
Notes:
The project's Review Data is organised into SCALPED lists.  
(1) Schedule
(2) Concerns - the main list of interest in the review.
      [a] Organisation and Staffing, 
      [b] Engineering and Facilities, 
      [c] Materials and Management, 
      [d] Execution Planning and Contracting, 
      [e] Cost, Schedule and Controls, 
      [f] Management Systems and Procedures, 
      [g] Government Regulations and Requirements, 
      [h] Other Areas (depending on project scope)
(3) Actions
(4) Locations
(5) People
(6) Events
(7) Deliverables
 
Task Information
Task Priority None
Start - Due Date 10/03/2017 - 25/03/2017
% Complete / Duration 0% of 16 Day(s)
Resources
IPR Service : SEND COMMENT